Timetable of Implementation
An indicative timetable for implementation of Civil Parking Enforcement (CPE) is as follows (subject to COVID-19 Cabinet arrangements in both Districts and County Councils).
MILESTONE |
DATE |
---|---|
CPE approval paper to Oxfordshire County Council Cabinet |
October 2020 |
CPE approval paper to Cherwell District Council Cabinet |
November 2020 |
CPE approval paper to South Oxfordshire District Council Cabinet |
December 2020 |
CPE approval paper to Vale of White Horse Cabinet |
December 2020 |
Draft application developed for the |
October 2020 - December 2020 |
Commencement of review of existing |
January 2021 - August 2021 |
Commencement of the Statutory |
February 2021 - April 2021 |
Application submitted to the Department for Transport |
April 2021 |
Department for Transport review & parliamentary process |
April 2021 - November 2021 |
Establishment of formal ‘back |
July 2021 - November 2021 |
Designation Order created and CPE |
November 2021 |